- Owner: CMWU
- Location: Khan Younis
- Duration: 2011-2012
- Type of Services:
The purpose of this project was to procure the services of a Detailed Design /Build Contractor to execute the detailed design and construction of upgrading Khanyounis temporary wastewater treatment plant.
The main components consisting of :
Inlet structure, Mechanical fine bar screen, Grit removal with mechanical cleaning and Sand classifier, converting anaerobic pond to aerated lagoon by adding aerators and splitting the final pond into settling pond and maturation pond and adding pipes and manholes with sluice gates.
- Note: